Home / Tools / Scope-Creep Cost Calculator
Free tool · Pricing
Scope-Creep Cost Calculator
One "quick extra round" rarely stays quick. Enter the hours you worked but never billed and your target hourly rate to see exactly what scope creep costs you on one project — and what it costs you across a whole year of projects. Everything runs in your browser; nothing you type leaves this page.
Hours beyond the agreed scope that you worked but did not charge for — extra revisions, added features, "just one more" meetings.
How many projects a year tend to grow past their original scope in the same way.
Leave this in to see how scope creep drags down your effective hourly rate. Clear it to hide that line.
Revenue lost per projectUnbilled hours × your rate
$0
Unbilled hours per yearExtra hours × projects per year
0
Effective hourly rate on the projectQuoted fee spread over quoted + extra hours
$0
Revenue lost per monthAnnual loss ÷ 12
$0
Revenue lost per yearPer-project loss × projects per year
$0
How the math works
- Revenue lost per project: unbilled extra hours × your target hourly rate. With 8 unbilled hours at $100/hour, that is $800 on a single project.
- Revenue lost per year: per-project loss × projects per year. At $800 across 12 projects, that is $9,600 a year of work you did for free.
- Effective hourly rate (optional): if the project was quoted at 40 hours × $100 = $4,000, but actually took 48 hours, your effective rate is $4,000 ÷ 48 = $83.33/hour — a 16.7% pay cut you gave yourself.
Contract clauses that stop scope creep
- Define the deliverable in writing. List exactly what is included — number of pages, revisions, formats, and features — so "one more thing" is visibly outside the deal.
- Cap revisions. State how many revision rounds are included (two is common) and that further rounds are billed at your hourly rate.
- Price change orders before you do the work. Any request outside the scope gets a written change order with its own price and deadline — no work starts until the client approves it.
- Set an hourly rate for extras in the contract itself. Naming the rate up front removes the awkward negotiation when the extra work arrives.
- Put a pause clause on unpaid extras. If a change order goes unpaid, work on that item pauses — you are not financing the client's scope expansion.
- Re-quote, don't absorb, a bigger project. If the scope doubles, the price should too. Use your annual loss number above as the reason: it is hard to argue with your own arithmetic.
More tools: Hourly Rate Calculator · Retainer vs. Project Pricing Comparator